The NBIMS-US™ v4 is a consensus-based national-level standard focused on defining standard approaches and guidelines to defining requirements, planning BIM adoption, and exchanging information between project team members. MORE
A project BIM execution plan (BEP) is developed by a project team through a collaborative process at various stages within the project deliverable (see Figure 1). As defined by ISO 19650-2 (2008), an owner (also known as the Appointing Party within the ISO standard) should define their BIM requirements and standards prior to the solicitation of delivery team members (known as lead Appointed Parties or Appointed Parties within ISO 19650-2).
Figure 1: Mapping BIM Execution Planning submissions to ISO 19650-2 processes
This Standard focuses on defining project-level BEPs at three stages within the delivery process. A core set of BEP information is needed from the owner for proposal organizations and selected team members to achieve the owner’s goals and align with the owner’s information management practices. The three stages in the Standard include:
Additional considerations regarding the project BEP:
The NBIMS-US™ v4 is a consensus-based national-level standard focused on defining standard approaches and guidelines to defining requirements, planning BIM adoption, and exchanging information between project team members. MORE